Patch panels, step by step.
One worked example, click by click: connect a switch in one rack to a server in another through two patch panels and the trunk between them. 8 steps, about five minutes.
What we are building
CORE-SW-01 is in Rack A and APP-SRV-01 is in Rack B. Each rack has a patch panel, and a trunk joins the two panels. A short patch lead at each end completes the run.
The one idea
A panel port does nothing on its own. It joins whatever is plugged into its front to whatever is plugged into its rear. Patch leads go on the front; fixed cabling and trunks go on the rear.
Before you start
You need the two racks, and the switch and the server added as devices with their ports. Any names will do; the guide uses the ones in the picture.
Create the two panels and the trunk
-
Step 1 of 8
Add the panel in Rack A
A patch panel is added like any other device; choosing the type is what gives it fronts and rears.
- Open Devices and click Add device.
- Name it PP-RACK-A and set Type to patch panel.
- Set Media type to copper, Ports to 24 and Connector to RJ45.
- Under Rack Assignment choose Rack A and U position 20.
- Leave “Rear is in” on Same rack, then click Create Device.
You should see: The panel is created with ports 01 to 24, each with a front and a rear, and it appears in Rack A at U20.
The form for PP-RACK-A. The panel fields appear once Type is patch panel. -
Step 2 of 8
Add the panel in Rack B and trunk it
The second panel is the far end of the trunk, so the form can cable all 24 ports for you as it creates them.
- Click Add device again. Name it PP-RACK-B and set Type to patch panel.
- Set the same Media type, Ports and Connector, then Rack B and U position 20.
- In “Trunk the rear to”, choose PP-RACK-A.
- Click Create Device.
You should see: A message confirms “Trunked 24 ports to PP-RACK-A”. The rear of every port on PP-RACK-B is now joined to the rear of the same-numbered port on PP-RACK-A: 01 to 01 through 24 to 24.
One choice in the form replaces 24 trips through the patch window.
Patch the switch and the server
-
Step 3 of 8
Open PP-RACK-A and pick a port
Every row is one port. The trunk is already showing on every rear.
- Open PP-RACK-A from the Devices list.
- Port 01 shows PP-RACK-B · 01 under Rear. Its front is still free.
- Click Patch front on port 01.
You should see: The Patch Through window opens on the Front, the one side of this port still to do.
After the trunk: every rear names its port on the other panel, and every front is free. -
Step 4 of 8
Front: plug in the switch
The front of the port is where the patch lead from the switch goes.
- In Device, type CORE-SW-01 and choose it.
- Choose its port, Gi1/0/1.
- Optionally give the patch lead a Cable ID, here PATCH-A-01.
- Click Next. The Rear step says it is already patched to PP-RACK-B · 01; click Next again.
You should see: Cable type is filled in for you from the two ports (copper patch).
The device on the front of PP-RACK-A port 01. -
Step 5 of 8
Review and create
One line shows the whole run before anything is saved.
- Check the line reads CORE-SW-01 · Gi1/0/1 ▸ PP-RACK-A · port 01 ▸ PP-RACK-B · 01 (already patched).
- Click Create Patch Through.
You should see: The patch lead is saved and the switch is now connected through to the other panel.
The trunk is named on the line, so you can see where this port leads. -
Step 6 of 8
Patch the server into PP-RACK-B
The last cable is the patch lead from the other panel's front to the server.
- Open PP-RACK-B and click Patch front on port 01.
- In Device, type APP-SRV-01 and choose its port, eth0.
- Click Next twice (the rear is already patched), then Create Patch Through.
You should see: The run is complete: switch, panel, trunk, panel, server.
The front of PP-RACK-B port 01 goes to the server.
Check it and trace it
-
Step 7 of 8
Read the port
The panel's own page is the quickest check.
- Look at port 01 on PP-RACK-B.
- Front names the server and Rear names the other panel. Click either to open that cable.
You should see: Port 01 is fully patched. Ports 02 to 24 have their trunk in place and a free front, ready for the next device.
Both sides of port 01 now say what they are patched to. -
Step 8 of 8
Trace the run end to end
This is the point of documenting panels: one click shows where a cable really ends up.
- Open any cable on the run, for example by clicking CORE-SW-01 on PP-RACK-A port 01.
- Scroll to Cable Path.
You should see: The path lists every hop in order: CORE-SW-01, PP-RACK-A port 01, PP-RACK-B port 01, APP-SRV-01.
The whole run, through both panels.
Trunk them from the panel's page
Open either panel and click Trunk to another panel. Choose the other panel and you see exactly what will happen before anything is saved.
- Ports are matched by number, rear to rear.
- A rear that already has a cable is left alone and listed as skipped.
- Panels of different sizes join the ports they share. Here a 24-port panel meets a 12-port one.
- A cable ID prefix labels every cable in the trunk: TRUNK-CD-01, TRUNK-CD-02 and so on.
Variations on the example.
Only one panel?
Leave “Trunk the rear to” on Not trunked. Click Patch through on a port, choose one device for the Front and another for the Rear, and the run is device ▸ panel port ▸ device.
Patching one side now, the other later
Tick Leave the front empty or Leave the rear empty. The port then shows Patch front or Patch rear for the side that is left.
Adding more ports later
On the panel's page, Bulk Add Ports adds a numbered run and carries on from the last number. Each new port gets a front and a rear.
Renaming a port
Click a port's name on the panel's page, type the new name and press Enter. The front and rear are renamed together, and any cable on the port stays in place and shows the new name.
A panel that spans two racks
Edit the panel and set “Rear is in” to the second rack. Its front shows in one rack and its rear in the other, and the wizard warns you if a cable would cross between them.
Panels on the topology map
Turn the Patch panels toggle off and each run through panels is drawn as one dashed cable between the two end devices. Turn it on to see the panels themselves.
Cassette panels
A chassis whose cassettes go to different racks, fed by MPO trunks, LC harnesses or copper trunks, needs a little planning: name each cassette's ports after its trunk. The cassette panel guide walks through it.
Fibre works the same way
Choose SM fibre or MM fibre as the media type and LC, SC or MPO as the connector. The steps are identical.